Abu Quir Power Station

Transporting 404 tons Generator Stator from Abou Quir Military Port up to Abou Quir Power Station

abuquir-1
abuquir-2
abuquir-3
abuquir-4
abuquir-5
abuquir-6
abuquir-7
abuquir-8

Main information:

a- Package Dimension:

Package Weight Length Width Height
Generator Stator 404.00 Tons 11.70 m 5.10 m 5.00 m

b- The transport operation was done on June 2011 from Abou Quir Military Port up to Abou Quir Power Station amounting 11,900 Kilometers.

c- Transporter Configuration: 1 x 3 x 16 Nicolas conventional hydraulic trailer .

d- Bottle Necks: The hardest Points in these maneuvers were the following:

  1. Removing rail way traffic lights post to enlarge the maneuver at El Maamoura railway crossing.
  2. Supporting 1 weak bridge using a special system based on transferring the load to the uplifting force of the water.
  3. Constructing a temporary railway crossing in front of the power station.

e- Suspension Setup: 3 points suspension A-Symmetric each group 16 pistons.

f- Transport arrangement drawings: