Transformers Transportation For Giza North Project

EGYTRANS had secured Giza North for Transformer Packages with (FH Bertling) this job includes the transportation of six Transformer Packages as follows: –

– Six Transformer Packages ( 7.42 m x 4.31 m x 5.10 m, 146 Ton) each
Also job is included all civil works form Port of Delivery – Adabiya & Sokhna Ports – till delivery to site, civil works included the followings:

  • Preparing El-Tebbin Quay storage area ground to be able to carry the loads
  • Constructing a temporary jetty at El-Khatatba to perform the operation

Job included receiving Transformers from vessel and storing them inside port on elephant legs & storage beams inside port using Low-bed Hydraulic system then re-loading again from port and transported to site via our hydraulic trailers on road up to El-Tebbin port then loading on barges through River Nile up to El-Khatatba temporary jetty then offloading from Barge and land transportation up to setting on foundation at site.

All six transformers received and transported safely to job site, first shipment had been arrived included 3 transformers and the second was an identical one, both shipments arrived on May 2013

Photo-1
Photo-2
Photo-3
Photo-4
Photo-5
Photo-6
Photo-7
Photo-8
Photo-9
Photo-10
Photo-11
Photo-12
Photo-13